Latest Articles

Escalating Data Center Applications Demand Speedy Grid Connection Outside Line

Escalating Data Center Applications Demand Speedy Grid Connection

By | Jul 20, 2026
Data center capacity is expected to grow from 24 gigawatt (GW) to 110 GW between 2026 and 2030, largely due to expansion of artificial intelligence and...
Putting Power to Good Use: States question grid buildout as capacity sits untapped Outside Line

Putting Power to Good Use: States question grid buildout as capacity sits untapped

By | Jul 15, 2026

For the last century or more, utilities have sized their grids to meet peak demand needs: those few hours during a year when electricity use soars. This approach has ensured lights stay on and air conditioning keeps running, even during summer’s hottest days.

Advertisement

More Outside Line Articles

View additional articles

Advertisement

Advertisement

Advertisement

Advertisement

featured Video

;

Turn Jobsite Minutes into Savings: Install & go with luminaires with wireless SensorSwitch AIR embedded controls

Because your time matters, there’s a faster way to add lighting controls. Choose luminaires with wireless SensorSwitch AIR embedded controls and install the luminaire and the controls, all in one. Get it easily through your local distributor.

Magazines

Immediate access as well as a brochure-style overview of EC Magazine, Safety Leader and Line Contractor.

View all

Advertisement