Transformer shortages now are high on the list of woes for utilities and data center developers. However, a new solid-state technology could help ease backlogs over the next two to three years, potentially boosting operational efficiency as well. The designs are proven and successful pilots are underway, but a hurdle remains to broad market acceptance: access to the same high-speed processors data centers are fighting over.
This fundamentally different approach to stepping power up and down is hitting the market just in time to support next-generation A.I. operations. Called solid-state transformers (SSTs), the equipment replaces steel and copper with semiconductors and software to convert power, route it from multiple sources and respond to load swings in seconds. It also is smaller and provides DC output, eliminating the need for rack-level inverters to convert the AC from traditional transformers to the DC power data equipment requires.
Leading manufacturers include startups Amperesand, DG Matrix and Heron Power, along with inverter manufacturers Enphase and SolarEdge. Eaton also recently entered this market with its purchase of Austin-based Resilient Power Systems.
Today’s bespoke approach
SST manufacturing is a modular process, unlike the old-school craftsmanship required to produce traditional transformers. SSTs are still constructed largely by hand, and their performance depends on the use of a specific metal—siliconized grain-oriented electrical steel (GOES), for which there is a single U.S. supplier for domestic manufacturers. With utilities and their data center customers competing for constrained production, delivery times for these bespoke devices now can extend beyond two years.
This shortfall is a recognized factor in the grid-connection backlog slowing A.I. data center development. Customers seeking large power transformers (those rated higher than 69 kilovolts) face particular challenges. First, more than 80% of these devices come from outside the United States, according to a U.S. Commerce Department report (though this figure could have shifted since its 2020 publication). So, U.S. data center developers face global competition—and pricing—for access to those products.
Additionally, building up U.S. capacity depends on creating new supplies of transformer components. For example, insufficient access to GOES and copper windings limits the number of transformers companies can produce. Both materials have their own involved manufacturing processes, which makes boosting output difficult.
Finally, because today’s large power transformers are custom designed and built, the kind of production lines used to create dishwashers and automobiles just aren’t feasible. These are highly engineered pieces of equipment, requiring artisan-like attention to detail. A recent New York Times Magazine article profiled transformer maker Delta Star, Lynchburg, Va., noting it takes five to seven years of winding experience at that company to be considered highly skilled. And, with more potential points of failure, traditional products also face more intensive testing to help ensure lifespans of 50 years or more in the field.
Fortunately, growing demand is pushing domestic manufacturers to boost their production capacity. In June 2025, Siemens Energy announced a $421 million investment in a new large power transformer facility to be built in Charlotte, N.C. And in June 2026, Hitachi broke ground on a $457 million expansion of its South Boston, Va., facility that the company says will roughly double the plant’s existing footprint. Additionally, Cleveland Cliffs, the nation’s only GOES fabricator, is in the middle of a $195 million update and expansion of its Pennsylvania Butler Works plant, home to its GOES operations.
None of these are short-term solutions, however. Siemens says its plant will open June 2027, while Hitachi and Cleveland Cliffs see their new lines starting up in 2028. And, as data center developers now seek to create their own on-site generation capabilities, competition is only growing for the limited supply manufacturers can now produce.
Semiconductors to the rescue?
SST technology is arriving just as new designs for the largest hyperscale data centers are beginning to move from the drawing board to reality. These facilities are planned around an 800V DC power architecture that promises to boost efficiency and reduce material costs.
The traditional approach, with power being distributed at 415V AC, requires multiple power conversions to step down voltage and convert to DC. Each of those operations creates power losses, adding heat that cooling systems must handle. With 800V DC, the same wire gauge can carry 157% more power than with 415V AC, according to chipmaker Nvidia, without need for heavier copper wiring to handle the larger load.
Unfortunately, SSTs are facing their own supply constraints, which are driving up costs. The semiconductors they depend on already face high demand from electric vehicle makers and A.I. data center electrical systems. The U.S. Department of Energy (DOE) has listed the semiconductors on its Critical Materials List, according to a February 2026 DOE report, meaning they face supply chain challenges through 2035 unless domestic manufacturing capacity expands. Resulting higher prices could slow uptake of SST technology just as it nears market maturity.