Appellate Court Ruling Eliminates Foundation for ComEd Smart Grid Pilot

Nov 15, 2010
generic image

Advertisement

Advertisement

Advertisement

Advertisement

You're reading an older article from ELECTRICAL CONTRACTOR. Some content, such as code-related information, may be outdated. Visit our homepage to view the most up-to-date articles.

Commonwealth Edison Co. (ComEd), a utility for the northern Illinois area, asked the Illinois Commerce Commission (ICC) for immediate action to redefine a path for Illinois’ first smart grid pilot in response to a Sept. 30 Illinois Appellate Court decision that effectively killed the study phase of the ICC’s plan for modernizing Illinois’ electric infrastructure. ComEd asked the ICC for a decision on a temporary measure that would transfer some of the costs of the pilot into ComEd’s general pending rate case instead of the rider.

In its petition, ComEd asked the ICC to approve a scaled-down version of its smart grid pilot program, the funding for which the Illinois Appellate Court eliminated in its September order. The pilot was designed to generate information that would feed into a longer term process established by the ICC and aimed at discerning what sorts of investments in grid modernization would best serve Illinois’ economic future. ComEd’s pilot is on hold until a decision is made.

“Many industry experts and state policy-leaders view grid modernization and smart grid technology as critical to future economic development,” said Anne Pramaggiore, president and CEO, ComEd. “As the United States economy emerges from the recent and devastating recession, high quality infrastructure will be a competitive advantage. ComEd wants to support Illinois in taking a leadership role.”

The pilot had planned a greater focus on customer interaction with new technology and its collaborative approach to pilot design involving more than 50 stakeholders in the state. The technologies being studied in the pilot hold promise in reducing electric system outages, enhancing communications between utilities and customers, and providing important information that would afford customers more control over their electricity usage and opportunities to reduce their bills.

“This temporary measure will enable ComEd to finish the study, but it is not a long-term solution,” Pramaggiore said. “Nevertheless, we believe it is critical that the ICC indicates its direction to move forward and keep the path to a future smart grid open.”

Advertisement

Advertisement

Advertisement

Advertisement

featured Video

;

Advantages of Advertising with ELECTRICAL CONTRACTOR in 2025

Learn about the benefits of advertising with Electrical Contractor Media Group in 2025. 

Advertisement

Related Articles

Advertisement